Common Ledger is independent and is not affiliated with, sponsored by, or endorsed by PayHOA. Product descriptions were reviewed against PayHOA's public materials on November 27, 2026; features, reports, services, payment methods, and interfaces change. This guide is general operational education, not accounting, audit, tax, legal, engineering, construction, banking, insurance, reserve-study, or investment advice. Use the association's governing documents, approved contracts, current reserve study, professionals, and actual project facts.
Capital projects fail in the gaps between systems
The contract may live in a document folder, approvals in minutes and email, invoices in accounts payable, payments in the bank, costs in the general ledger, and progress in a contractor's schedule. None of those records alone answers the board's basic questions. A controlled process connects authority, scope, commitments, work completed, funding, payment, reporting, and closeout.
PayHOA currently describes a general ledger, custom chart of accounts, transaction splits, bank reconciliation, payables, approval rules, vendor records, budgets, more than 40 reports, report packets, and document storage. Those tools can organize evidence. They do not certify construction progress, interpret a reserve study, authorize a contract, approve a change order, determine capitalization or tax treatment, or replace board and professional review.
1. Open the project before the first invoice
Create a project register when the board begins spending, not after invoices arrive. Give the project a stable name and identifier. Record the asset or system, objective, location, responsible director or committee, manager, engineer or consultant, contractor, approved procurement method, board authorization, contract date, notice to proceed, expected start and finish, warranty, insurance requirements, and records location.
Separate the original contract amount, allowances, alternates, contingency, approved change orders, pending changes, owner-direct purchases, professional fees, permits, testing, temporary protection, financing costs, and estimated remaining cost. The register should show both total approved authority and current forecast. A general-ledger balance shows recorded transactions; it does not automatically show unbilled commitments or pending decisions.
2. Confirm funding authority and source
Document whether the project is funded from operating cash, reserves, a special assessment, loan proceeds, an insurance recovery, or a combination. Tie the decision to the budget, reserve study, board action, owner approval when required, governing documents, bank arrangements, and professional advice. Do not label spending as a reserve draw merely because cash came from a savings account.
Prepare a funding schedule with beginning available cash, board-authorized amount, transfers, assessment collections, loan draws, insurance advances, interest, project disbursements, reimbursements, and remaining available funding. Keep restricted, designated, or legally constrained amounts distinct under the association's actual rules and accounting method.
3. Build the accounting map
Before posting activity, decide with the association's accountant how the project will appear in the chart of accounts and reports. The design may use one project account, subaccounts by phase or asset, or a controlled supplemental schedule tied to the ledger. Use a structure the board can understand and the CPA can reproduce.
Map contract work, professional services, permits, temporary measures, owner reimbursements, insurance recoveries, retainage, deposits, interfund transfers, loan activity, and disposal or replacement of existing assets. Establish the documentation needed for every posting and how corrections will be approved. Avoid a catch-all project account that hides material categories and a hyper-detailed structure nobody can maintain.
4. Preserve the contract baseline
Store the signed agreement, exhibits, scope, drawings, specifications, schedule of values, allowances, payment terms, retainage terms, bonds if any, insurance certificates, permits, warranties, change-order process, lien-release requirements, dispute terms, and contact list in an association-controlled location. PayHOA currently describes vendor records for contracts, insurance certificates, payment history, and notes, plus a document library with configurable sharing.
Record the baseline in the project register. A board should be able to reconcile the register to the executed contract without interpreting a stack of proposals. If the contractor's schedule of values changes, retain the prior version and approval rather than silently replacing it.
5. Control deposits and advance payments
A deposit is not proof that work was performed. Before paying, confirm contract authority, amount, due date, payment security, vendor identity, bank details, insurance, required bonds or protections, board approval, and the accounting treatment selected by the CPA. Record how the advance will be applied to later invoices.
Track every deposit separately until it is earned or otherwise resolved. Reconcile the deposit schedule to the ledger and vendor statement. The project register should show the original deposit, applications, refunds, disputed amounts, and remaining balance.
6. Route every invoice through the same evidence chain
PayHOA currently describes invoice intake by email or upload, payable creation from an attachment, approvals based on amount, and check payment options, plus ACH for associations with the PayHOA financial account. Configure the workflow around the association's actual authority. For each invoice, capture the vendor, invoice number, date, period, project ID, contract line, prior billed amount, current billing, stored materials if allowed, retainage, approved change orders, tax, credits, amount due, and funding source.
Require evidence that the work or milestone was reviewed by the appropriate manager, board representative, engineer, architect, or other professional. Preserve the invoice, schedule of values, site or professional review, approval, exceptions, lien documentation where applicable, and payment record. Accounting staff should not be asked to certify physical completion they cannot observe.
7. Treat change orders as new commitments
No change should enter the project forecast only when the invoice arrives. Maintain a log with request date, reason, scope, price, schedule impact, alternatives, professional recommendation, funding impact, approval authority, decision date, signed document, and accounting code. Distinguish a proposal, pending change, construction directive, allowance use, field condition, and executed change order.
Update the commitment total and forecast after approval. If emergency work proceeds under delegated authority, preserve the facts, authorization, notice, and subsequent ratification required by the association's rules. Do not backfill approval language simply to make the accounting file appear complete.
8. Reconcile reserve draws and interfund transfers
For each transfer, record the board authority, source account, destination account, amount, date, purpose, related invoices, bank confirmations, and ledger entries. Confirm the transaction appears once in each cash account and is not also misclassified as income or expense. Tie the cumulative draw to project costs and the reserve schedule.
Keep cash movement separate from expense recognition. A transfer may fund the operating account before a bill is paid, while a bill may be recorded before cash moves. Present beginning reserve cash, transfers, direct reserve payments, reimbursements, interest, and ending reserve cash in a way that reconciles to both bank and ledger.
9. Track retainage, unpaid bills, and remaining commitments
Maintain a schedule showing contract amount, approved changes, revised contract, gross billed, retainage, net billed, payments, unpaid approved invoices, disputed amounts, pending changes, estimated cost to complete, and forecast final cost. Reconcile it to the vendor history, payable list, general ledger, bank, and project professional's payment records.
At month-end and year-end, ask whether work performed but not yet billed, approved retainage, unresolved claims, or other commitments require accrual, disclosure, or separate reporting. The CPA should determine accounting treatment. The board still needs an operational forecast even when an amount is not yet recorded in the general ledger.
10. Separate insurance proceeds and claim costs
If a project follows an insured loss, maintain a claim schedule for loss date, coverage, deductible, emergency work, mitigation, adjuster estimates, contractor costs, recoverable depreciation, advances, reimbursements, direct payments, owner responsibility, exclusions, professional fees, and open claim items. Do not net every receipt against project cost without the CPA's direction.
Reconcile insurer payments to bank records and claim correspondence. Identify whether a check includes multiple buildings, losses, vendors, mortgagees, or categories. Give the board a view of total project cost, insurance recovery, association-funded amount, owner-funded amount, and unresolved claim exposure.
11. Produce a monthly project packet
A useful board packet combines the project register with accounting reports and operational status. Include approved budget or authority, original and revised contract, paid-to-date, current payables, retainage, commitments, pending changes, forecast final cost, funding sources, reserve draws, cash available, schedule status, key risks, claims, disputes, permits, decisions required, and exceptions.
PayHOA currently describes reports, date filters, PDF and CSV output, and report packets. Select reports that tie to the project schedule and preserve the settings and run date. The packet should explain why the project schedule and ledger differ when one includes commitments or forecasts the other does not.
12. Reconcile monthly and protect cutoff
Reconcile every project bank and investment account, then tie cash, transfers, invoices, payables, payments, and credits to the project register. Review transactions posted outside the payable workflow, duplicate invoices, checks not cleared, returned ACH, credit-card costs, generic vendor names, journal entries, and activity dated before or after the correct period.
Use a close checklist with preparer, reviewer, evidence, exception, and resolution. When an invoice or change arrives after the board packet, label the packet's cutoff and show the item in the next forecast rather than silently changing a previously distributed report.
13. Prepare the tax and vendor-reporting file
Confirm vendor legal names, tax information, payment totals, payment methods, reimbursements, credits, and amounts paid outside PayHOA. PayHOA currently describes vendor payment history and 1099 support. The association's tax adviser should determine forms, classifications, thresholds, exclusions, filing method, corrections, and deadlines using current law and complete payment records.
Separate contractor compensation from materials, owner reimbursements, insurer direct payments, card-processed payments, and other categories only under professional guidance. Preserve the source evidence and reconciliation rather than relying on a software eligibility flag as the tax conclusion.
14. Close the project deliberately
Do not mark a project complete when the last large invoice is paid. Confirm final inspection or acceptance, punch-list closure, approved changes, final invoice, retainage release, lien or claim documentation as applicable, permits, certificates, warranties, manuals, as-built information, keys or access credentials, spare materials, training, insurance notice, asset records, reserve-study updates, and unresolved disputes.
Reconcile the final contract schedule to the ledger, payables, bank, reserve activity, insurance schedule, and board authorization. Record final cost, funding by source, variance from budget, remaining cash, accounting adjustments, capitalization or expense treatment determined by the CPA, and lessons for the next project.
15. Export a portable project archive
Download the final reports, transaction detail, vendor history, invoices, approvals, contracts, change orders, correspondence, bank support, funding schedule, insurance records, minutes, and closeout documents. Open the export, test totals and links, label the accounting basis and date range, and store it under association control with retention and access rules.
The archive should survive a change in board, manager, accountant, contractor, bank, insurer, or software. Include a data dictionary for project IDs and account codes, an exception memo, unresolved warranty or claim calendar, and instructions for retrieving records. A portal is useful access; it should not be the association's only memory.
Sources and related guides
- PayHOA: accounting, chart of accounts, journal entries, and bank reconciliation
- PayHOA: payables, approvals, vendor records, and payment history
- PayHOA: budgets, reports, exports, and report packets
- PayHOA: document storage and sharing
- Common Ledger: PayHOA reserve transfers and reporting
- Common Ledger: PayHOA vendor bill approval workflow
- Common Ledger: PayHOA month-end close checklist
- Common Ledger: PayHOA year-end close checklist